2020 Pinery Neighborhood Street Paving

 

On each street, work will be done in two phases -

  • Phase 1 consists of rotomilling to remove some of the top layers of asphalt, which generally takes 2 to 4 hours or less per block to complete. 
  • Phase 2 follows a week or two later and includes placing the new overlay; whis phase may take 4 - 8 hours to complete. During contruction access to driveways is allowed, with occasional short delays.

Two days before the start of construction, no-parking signs are posted along the streets scheduled for work. Construction will be done Monday through Friday between 7 a.m. - 7 p.m.

Work on the 2020 program will begin May 18 and be completed by the end of June. 

 

View weekly schedule.

You may also go to the Douglas County website for more information.

 